Final report - June 2002 Issued by the Hazardous Installations Directorate (HID): Land Division
This report sets out HSE's monitoring requirements and associated enforcement action criteria for the iron mains replacement activity planned by Transco for the period 1st April 2002 to 31st March 2007.
Contents
- Executive Summary
- 1. Basis for the mains replacement programme and HSE monitoring
- 2. Transco's management and monitoring systems
- 2.1. scheduling & monitoring
- 2.2. Initial Planning
- 2.3. Phasing of workload
- 2.4. Workload Forecasting
- 2.5. Risk Profile
- 2.6. Current monitoring and reporting arrangements
- 3. HSE's information requirements
- 3.1. Planning and Implementation
- 3.2. Routine monitoring and Control
- 3.3. Reporting Framework and Communications
- 3.4. Exception reporting
- 3.5. Target Risk Score Profile of annual work programmes
- 3.6. Use of Risk Profile Information
- 3.7. Proactive Monitoring & Audit
- 3.8. Transitional arrangements during 2002 - 2003
- 4. Year end review
- 5. The role of HSE in enforcing the mains replacement programme
Tables
- Table 1 Typical planning phase milestones in a normal output-reporting year
- Table 2 Possible Key Target Dates for submission of data to HSE
- Table 3 Initial Exception Reporting Thresholds
- Table 4 Transitional Period Exception Reporting Thresholds
Appendices - For illustrative purposes only
- App. 1 National 5 Year Forecast (2002/3 -2006/7)
- App. 2 Example Network 5 Year Forecast (2002 - 2007)
- App. 3 National Phased Annual Programme (2002/3)
- App. 4 Example Network Phased Annual Programme (2002/3)
- App. 5A Routine Quarterly Report: Summary page (Dec 2001)
- App. 5B Routine Quarterly Report: Data table (Dec 2001)
- App. 5C Cumulative Performance Charts (Dec 2001)
- App. 5D MP DI Replacement (June 2002).
- App. 6 Iron Mains Risk Score Profile (MRPS version 5)